From an email:
Folks:
As with every project where there are many players, schedules change – this one is NO EXCEPTION. Some of the paving work that was supposed to have been completed last night wasn’t; therefore, our paving schedule for tomorrow has changed a bit.
Here are the details:
Beginning tomorrow, 10/25/2018 at approximately 9:00 AM and ending at approximately 12:30 PM, the final course of pavement will be placed on Vista Circle between Shore Drive and Cape Henry Drive, as well as Cape Henry Drive from Vista Circle to the entrance to Bubba’s Restaurant. This work will require intermittent street closures of both Vista Circle and Cape Henry Drive, so please plan accordingly.
Paving crews will move to the west side of the bridge (East Stratford Road) immediately after paving is completed on Cape Henry Drive.
Paving work on East Stratford Road and Piedmont Circle will begin tomorrow, Thursday 10/25/2018 at approximately 1:00PM. Therefore, beginning at approximately 1:00 PM and ending some time near 10:00 PM on 10/25/2018 expect East Stratford Road to be CLOSED between Piedmont Circle and Shore Drive and Piedmont Circle to be CLOSED between East Stratford Road and the showers at Lynnhaven Boat Ramp while paving operations are underway. Paving crews will also attempt to pave the RIGHT TURN lane on eastbound Shore Drive at East Stratford Road (the one in front of J&A Racing) during this same time period.
Finally, on Friday 10/26/2018, expect single lane closures on both eastbound and westbound Shore Drive between Vista Circle and East Stratford Road between the hours of 9:00 AM and 3:00 PM. On eastbound Shore Drive crews will be placing the permanent pavement markings on the asphalt pavement between East Stratford Road and Vista Circle. On westbound Shore Drive crews will be working on sidewalk and utility work along the north side of Shore Drive.
We will continue to provide updates on anticipated lane/street closures as we near the final stages of this work.
PLEASE Drive Carefully through this work zone as we complete this work.
Sincerely,
-ChrisChristopher J. Wojtowicz, PE
Engineering Construction Manager
City of Virginia Beach
Department of Public Works
Engineering Division
2405 Courthouse Drive
Virginia Beach, VA 23456-9031
Office: (757) 385-5785
Fax: (757) 385-5668
Email: cwojtowi@vbgov.com