The construction at Greenwell and Shore Drive is for the new LEED certified Fire Station.
City of Virginia Beach, VA |
Public Works |
Capital Project Detail Sheet |
|
3.244.000: Fire and Rescue Station – Chesapeake Beach |
Description and Scope |
CIP Section: |
Buildings |
CIP Status: |
Approved |
Active |
Project Type: |
Replacement |
First Year in CIP: |
|
|
Business Area: |
|
|
|
|
City District(s): |
Bayside |
|
This project replaces the existing 9,760 square foot facility supporting 4 Fire and 2-to-5 Emergency Medical Services (EMS) personnel, 1 fire engine and 1 ambulance on a daily basis, and various other pieces of equipment that are infrequently used (ranging from fire trucks to zodiac boats). The existing facility has 2 drive through bays (2 vehicle capacity each) and 3 front load only bays (1 vehicle capacity each). The replacement will be a more efficient 3-bay facility ranging from 13,800 to 14,200 square feet based on the General Booth and Sandbridge stations. Cost estimates were based on 14,000 square feet. The replacement facility will house both Fire and EMS personnel and equipment. The new site will be at the intersection of Shore Drive and Northampton Boulevard. This facility is priority 10 on the City’s Top 13 Facility Replacement Priority list. |
Points of Contact |
Project Manager: |
Public Works |
John E Gresock |
(757)-385-4131 |
|
Schedule of Activities |
Project Activity |
|
Approved Budget |
|
Current Estimates |
Code |
Description |
|
Start |
End |
Cost |
|
Start |
End |
Cost |
2000 |
Design |
|
07/01/2010 |
06/30/2011 |
300,150 |
|
10/01/2010 |
02/01/2012 |
300,150 |
3000 |
Site Acquisition |
|
01/15/2007 |
09/18/2008 |
1,623,800 |
|
07/01/2007 |
09/30/2009 |
1,623,800 |
5000 |
Construction |
|
07/01/2011 |
12/31/2013 |
3,117,435 |
|
02/27/2012 |
07/22/2013 |
2,701,350 |
8000 |
Furniture and Fixtures |
|
07/01/2012 |
12/31/2013 |
261,000 |
|
08/01/2012 |
08/01/2013 |
261,000 |
9000 |
Contingencies |
|
01/01/2007 |
06/30/2013 |
362,500 |
|
07/01/2007 |
08/01/2013 |
362,500 |
Overall Project Start, End & Cost: |
|
01/01/2007 |
12/31/2013 |
5,664,885 |
|
07/01/2007 |
08/01/2013 |
5,248,800 |
|
|
|
Current Status and Progress |
A contract award to P.G. Harris/HBA was made with a Notice to Proceed date of February 27, 2012. Under the 511 day schedule proposed by the Design/Build Team, the project is scheduled to be substantially complete by July 21, 2013. The site plan has gone through several submittals to DSC and review comments have been received. Fina DSC approval was received at the end of August, and demolition of the existing structures on the site commenced on September 26. The existing concrete pavement has been removed from the site and the building pad has been graded. DVP is preparing a proposal to remove two utility poles on the site. |
Last updated: 10/23/2012 10:18:45 AM |
|
|
|
|
|
|
|
Like this:
Like Loading...
Related
Leave a Reply